Special Bridges
10 November, 2022
Atul Joshi, Vice President (Structure), Dilip Buildcon Limited told PTI that the first phase comprising four lanes is "almost complete" and would be ready for the traffic flow once load testing is done and crack barriers are installed.
26 December, 2022
Gadkari will formally inaugurate the partially completed section of the 13.2 km Zuari bridge– a crucial link between north and south Goa across the river Zuari
The inauguration of the first phase (northbound carriageway) will take place on December 26 by the hands of union minister of road transport and highways Nitin Gadkari, whose vision was to make this bridge a reality, Goa chief minister Pramod Sawant announced on Friday. The bridge will be thrown open for public on the same day, the CM said.
01 January, 2016
Union Road Transport and Highways Minister Nitin Gadkari today laid foundation stone for the Rs 2,700 crore cable-stayed parallel bridge on Zuari river, 15 kms off here.
02 January, 2019
While a four-lane section of the new eight-lane Zuari bridge is going to open for use by December 2019, the other four-lane section will be ready for use only in 2021 or 2022, public works department minister Ramkrishna Dhavalikar said on Tuesday.
Just four months ago, Dhavalikar had announced that the new Zuari bridge would be opened for use ahead of its schedule of 2021.
27 May, 2019
Panaji: Chief minister Pramod Sawant on Tuesday said that work on the third Mandovi bridge and one lane of the new Zuari Bridge will be completed before Dec.19.
17 April, 2021
PANJIM: If deadlines are met, traffic delays on the Panjim-Margo route could end by Liberation Day this year. The four-lane section of the signature Zuari bridge is likely to be thrown open for vehicular traffic from December 19 this year even as the work was delayed due to COVID-19 pandemic.
Zuari Bridge
On Going
Zuari cable stayed bridge is a high demand project as the existing bridge in Zuari River connecting Panjim and Mangalore does not cater to heavy vehicle movements due to its poor condition.
Construction of the Zuari cable stayed bridge includes building a bridge across the river Zuari on NH-17/ NH 66 on Panjim – Mangalore section in the State of Goa. The Zuari cable stayed bridge is 640m long with central navigational span of 360m and end span on both sides of 140m. This makes the bridge the 2nd longest and widest cable stay bridge in India. A tourist observatory and restaurant at the 110m high tower is planned on the bridge.
Zuari cable stayed bridge has 8 (4+4) lanes with 27m wide dual carriageways and a centre median of 10.7m. Bridge deck is of composite structure (steel structure and concrete) with a temporary steel walkway connecting both sides of embankments and pylon foundation locations for construction logistics. The bridge deck is fabricated at site using high tech robotic welding equipment. It is transported by barge into the river, where it is lifted and erected by lifting frames.
DBL has joined hands with a Ukraine based company, Mostobudivelnyi Zahin Limited (MBZ) with a 74% and 26% stake respectively, to construct the cable stay bridge. MBZ has experience in construction of bridges including suspension bridge of 840 metres with a central span of 520 metres and is the technical partner to Dilip Buildcon Limited for this project. MBZ’s involvement is to support in design, technical matters and execution.
Equipment used for this bridge includes 55 x 15 m Dumb Barge, 12 x 8 m Dumb Barge, 25 x 10 m Dumb Barge, 60 x 13 m Dumb Barge, MAIT Piling Rigs, Tower Cranes, and Robotic Welding System Equipment.
NHAI
22km
4 lane
On Going
The Rs 1,900 crore road project, which will include a four-lane bridge over the Ganga river, will connect Sahibganj bypass in Jharkhand to Manihari bypass in Bihar.
The scope of the work envisages construction of 15.885 km new link (NH-133B), including 6 km long Ganga bridge connecting Jharkhand with Bihar, construction of 6 km Manihari bypass and widening of NH-131A ending near Narenpur to 4 lane standard in Bihar.
MoRTH
2.125km
On Going
Construction of extra-dosed bridge across Sharavathi backwaters and approaches between Ambargodu and Kalasavalli of NH-369E. The length of the bridge is 2,125 mtr and approaches on both sides is 4.055 km.
The estimated cost of the project is Rs 3,600.9mn. The project is to be completed in 36 months.